When the Central Ecological Environmental Protection Inspector is in progress, Aksu: Clean up solid waste and build a green enterprise

On April 9th, the general solid waste landfill in the factory area of ​​Aral City Runjiang Plastic Industry Co., Ltd. has been completely disposed of, and the ground Make leveling. Photo by Correspondent Lv Na

Pomegranate Cloud/Xinjiang Daily News (Reported by reporter Wang Yayun and Correspondent Lv Na Jiawen) “Before, I had little awareness of environmental protection and landfilled some solid waste. In the future, I will strictly observe environmental protection and safety. Red line, make every effort to build a green enterprise.” On April 9, Cai Zhongren, the head of Aral City Runjiang Plastic Industry Co., Ltd., finally breathed a sigh of relief when he looked at the solid waste landfill pit that was basically leveled in the factory yard.

A few days ago, after receiving the letter from the Central Fifth Ecological Environmental Protection Inspectorate to assign “Alar City Runjiang Plastic Industry Co., Ltd. to bury hazardous waste”, the Aksu region attached great importance to it and arranged for relevant information in a timely manner. The staff went to the scene to check.

The investigation found that the Aral City Runjiang Plastic Industry Co., Ltd., located 4 kilometers away from the 219 National Highway, is in the jurisdiction of Aksu City, mainly producing and processing waste plastic granules. The main problem reported by letters and visits is that the company filled the waste water sedimentation tank sediment and a very small amount of raw materials mixed into it in the production process to the southeast corner of the factory area, and the earth and stone was about 200 cubic meters.

“After receiving the rectification request, we immediately found excavators and transport vehicles to remove all 200 cubic meters of earth and stone to the Aksu Economic and Technological Development Zone Solid Waste Landfill for standardized disposal.” Cai Zhongren said that he has deeply realized his mistakes, and will study more environmental laws and regulations in the future, strictly abide by them, operate in a law-abiding manner, and will never damage the ecological environment.

“General solid waste cannot be landfilled at will. While we put forward rectification requirements for enterprises, we have carried out publicity and education.” Wang Junbo, deputy director of Aksu City Branch of Aksu Regional Ecological Environment Bureau, said that during the rectification process , The environmental protection department has identified the landfill solid waste and judged it as general solid waste according to the raw materials and production process.

According to our understanding, Aksu Region has transferred petitions and reports to the Fifth Central Ecological and Environmental Protection Inspectorate to investigate and verify problems as soon as possible, and conduct strict and factual investigations. ? . At the same time, focusing on the key points of regional ecological and environmental protection work, we will earnestly carry out special law enforcement inspections of self-examination, self-correction, and inferences from one case to another. Through the rectification results of the central ecological and environmental protection inspectors, we will further recognize the work gap, strengthen the sense of responsibility, identify the target direction, and effectively Take environmental responsibility on your shoulders and put it into action.